Data Center Transformers

Compare pad-mount, dry-type, cast coil, and unit-substation transformers on rating, voltage, cooling class, K-factor, and lead time. Selection logic and used-market intelligence for data center buyers.

About this Category

Pad-mount, substation, and unit-substation transformers across utility, industrial, and data center applications. Verified kVA, primary/secondary voltage class, BIL, and cooling type across new OEM, refurbished, and used inventory.

The 10 transformers dossiers to read first, ranked on tracked availability, documented specifications, and published pricing rather than alphabetically. All 32 dossiers in the category are listed further down the page.

  1. Hitachi Energy Ltd (ex-ABB Power Grids) 10-40 MVA power transformer class — $6K–$650K used · lead time 2-12 weeks
  2. Virginia Transformer Corp (incl. Georgia Transformer) Pad-mounted oil-filled transformers (to 10 MVA) — 67,000 MVA · lead time 1-8 weeks
  3. Hyosung Heavy Industries / Hyosung HICO, Ltd. (Memphis, TN) EHV/UHV power transformers (69-765 kV, to 2,250 MVA) — 2,250 MVA · lead time 2-12 weeks
  4. Hitachi Energy Ltd Mobile substations (to 120 MVA / 420 kV) — 120 MVA · lead time 2-12 weeks
  5. Niagara Power Transformer LLC (Buffalo, NY) Liquid-filled substation transformers (to 50 MVA / 138 kV) — 50 MVA · lead time 2-12 weeks
  6. WEG S.A. (mobile transformers Brazil; integration by Zest WEG) Mobile substations (50 MVA class observed) — 50 MVA · lead time 2-12 weeks
  7. Hitachi Energy Ltd (line launched as ABB HiDry72) HiDry dry-type power transformer (above 40.5 kV, to 72.5 kV) — up to 63 MVA · lead time 2-12 weeks
  8. Hitachi Energy Ltd (ex-ABB Power Grids) HV/EHV power transformer legacy class (69-765 kV) — lead time 2-12 weeks
  9. Delta Star, Inc. (employee-owned ESOP) Mobile substations (to 133 MVA / 345 kV) — lead time 2-12 weeks
  10. Eaton Corporation plc DS-3 / DT-3 ventilated dry-type — lead time 1-2 weeks (dealer stock)

Data Center Transformers Models (32)

Every model below has a specification dossier with verified ratings, pricing context, and lead-time intelligence.

Compare Data Center Transformers (32 models)

Every published model in this category, compared on the specifications a data center buyer filters on first. Values come from each model dossier; an em dash means the specification is not documented, never an estimate.

ModelOEMTypeRatingPrimary voltageSecondary voltageCooling classImpedanceK-factorLead time
MD-series motor drive isolationEaton Corporation plcLV Dry-Type7.5-1500 kVAK-4 / K-13 / K-20New: Distributor quote; class stock ships 3-5 business days (Maddox) · Used: 1-2 weeks (dealer stock)
K-Factor rated dry-type transformers (K-4 / K-9 / K-13)MGM Transformer Company (Commerce, CA)LV Dry-Type15-1,000 kVA480 / 600 V delta208Y/120, 480Y/277150 CK-4 / K-9 / K-13New: Stocked sizes fast-ship; 20-32 weeks class otherwise · Used: 1-4 weeks (dealer stock)
Three-phase pad-mounted transformers (30-3,000 kVA)ERMCO (subsidiary of Arkansas Electric Cooperatives, Inc.)Pad-Mount Distribution30-3,000 kVA2.4-35 kV65 CNew: 40-65 weeks (pad-mount class) · Used: 1-8 weeks
Envirotran FR3 pad-mounted transformersEaton Corporation plc, Cooper Power seriesPad-Mount Distribution45-10,000 kVA2,400-34,500 V120-15,000 VNew: 80-120 weeks OEM; stock units 1-2 business days · Used: 1-8 weeks
DS-3 / DT-3 ventilated dry-typeEaton Corporation plcLV Dry-Type112.5 kVA – 10,000 kVA2.4 kV – 34.5 kV208V – 4,160V150 std; 115 / 80 optional CNew: Distributor stock to 20-32 weeks by size · Used: 1-2 weeks (dealer stock)
FITformer fluid-immersed distribution transformersSiemens Energy AG (Grid Technologies)Substation (Liquid-Filled)421M USD Charlotte NC250-800 VNew: 40-65 weeks pad-mount class; 65-95 weeks substation class · Used: 2-12 weeks
Pad-mounted transformers (500-7,500 kVA)Pennsylvania Transformer Technology, Inc. (a Quanta Services company)Pad-Mount Distribution500-7,500 kVANew: 40-65 weeks (pad-mount class); PTT-specific figures unpublished · Used: 1-8 weeks (class channel)
Liquid-filled substation transformers (750-20,000 kVA)Hitachi Energy LtdSubstation (Liquid-Filled)750-20,000 kVA69 kVNew: 65-95 weeks (5-25 MVA class) · Used: 2-12 weeks
10-40 MVA power transformer classHitachi Energy Ltd (ex-ABB Power Grids)Power & Substation (Oil-Filled)10-40 MVA base69-138 kVNew: 128-144 weeks (class average) · Used: 2-12 weeks
Large power transformers (10-350 MVA US; to 500 MVA Brazil)WEG S.A. (WEG Transformers USA, Washington, MO)Power & GSU (Oil-Filled)10-350 MVA24.94-400 kVONAN / ONAF / ODAF / KNAN / KNAFNew: Quoted; class 120 weeks average, 80-210 weeks large · Used: 2-12 weeks
Liquid-filled substation transformers (to 50 MVA / 138 kV)Niagara Power Transformer LLC (Buffalo, NY)Substation (Liquid-Filled)50 MVANew: 65-110 weeks (class, by MVA band); Niagara-specific figures unpublished · Used: 2-12 weeks
TMC cast-resin dry-typeTRAFO Power Solutions (Pty) Ltd (TMC Transformers S.p.A. partner)Cast-Resin Dry-Type50 kVA-25 MVAAN / AF / AFAF / AFAW/WFNew: Engineered to order via TMC Italy; no published lead times · Used: No used channel observed
Mobile substations (50 MVA class observed)WEG S.A. (mobile transformers Brazil; integration by Zest WEG)Mobile Substation50 MVA110 / 60 (dual-rated) kV20 / 30 kVNew: Engineered to order; quoted per project · Used: 2-12 weeks
RESIBLOCHitachi Energy LtdCast-Resin Dry-Typeup to 63 MVA36 kV24 kVNew: 20-32 weeks (dry-type class) · Used: 2-12 weeks
HiDry dry-type power transformer (above 40.5 kV, to 72.5 kV)Hitachi Energy Ltd (line launched as ABB HiDry72)Cast-Resin Dry-Type100 kVA – 40,000 kVA (40 MVA)Up to 36 kVUp to 3.3 kVAN/AFNew: Engineered to order; dry-type class 20-32 weeks at small MVA, longer at power class · Used: 2-12 weeks
EconiQ power transformer portfolio (natural ester)Hitachi Energy LtdPower & Substation (Oil-Filled)115/21 kV, 40 MVANew: 128 weeks class average; project-quoted · Used: 2-12 weeks
Mobile substations (to 120 MVA / 420 kV)Hitachi Energy LtdMobile Substation120 MVANew: Engineered to order; quoted per project · Used: 2-12 weeks
Trihal cast-resin dry-type transformerSchneider Electric SECast-Resin Dry-Type160 kVA-15 MVA36 kVNew: 20-32 weeks (dry-type class) · Used: 1-8 weeks (European dealers)
Pad-mounted oil-filled transformers (to 10 MVA)Virginia Transformer Corp (incl. Georgia Transformer)Pad-Mount Distribution500 kVA – 100 MVA4.16 kV – 230 kV480V – 34.5 kVONAN/ONAF/OFAFNew: 40-65 weeks (pad-mount class); company markets shortest-lead-time positioning · Used: 1-8 weeks
Generator step-up transformers (to 1,000 MVA / 765 kV)GE Vernova Inc. (Prolec GE, incl. Prolec-GE Waukesha)Power & GSU (Oil-Filled)600 1-phase / 900 3-phase MVA69-765 kV wye13.2-25 kV deltaONAN / ONAF / ODAFNew: 100-150+ weeks (GSU class); 144 weeks Q2 2025 average · Used: 2-12 weeks
EHV/UHV power transformers (69-765 kV, to 2,250 MVA)Hyosung Heavy Industries / Hyosung HICO, Ltd. (Memphis, TN)Power & GSU (Oil-Filled)2,250 MVANew: Contract-scheduled; class high-capacity leads to 4 years · Used: 2-12 weeks
Mobile substations (to 133 MVA / 345 kV)Delta Star, Inc. (employee-owned ESOP)Mobile SubstationNew: Engineered to order; quoted per project · Used: 2-12 weeks
Envirotran hardened data center pad-mounted transformerEaton Corporation plc, Cooper Power seriesPad-Mount DistributionNew: 80-120 weeks OEM pad-mount class; dedicated data center programs faster · Used: No used channel yet
HV/EHV power transformers (Montgomery, AL)HD Hyundai Electric Co., Ltd. (HD Hyundai Power Transformers USA, Montgomery AL)Power & GSU (Oil-Filled)New: Contract-scheduled; class 120 weeks average, 80-210 weeks large · Used: 2-12 weeks
TXpand rupture-resistant tank systemHitachi Energy LtdPower & Substation (Oil-Filled)New: Follows host power transformer (128 weeks class average) · Used: 2-12 weeks
HV/EHV power transformer legacy class (69-765 kV)Hitachi Energy Ltd (ex-ABB Power Grids)Power & Substation (Oil-Filled)69-765 kVNew: 144 weeks average (GSU); up to 4 years high-capacity · Used: 2-12 weeks
Three-phase pad-mounted transformers (45-10,000 kVA)Howard Industries, Inc. (Howard Power Solutions)Pad-Mount DistributionNew: 40-65 weeks (pad-mount class) · Used: 1-8 weeks
Unit substation and medium power transformers (225-10,000 kVA)Howard Industries, Inc. (Howard Power Solutions)Substation (Liquid-Filled)2,400-69,000 V120-8,400 V or 14,400YOA (+FA option) / 65 CNew: 65-95 weeks (substation class) · Used: 2-12 weeks
Power and substation transformers (5-750 MVA, to 765 kV)Pennsylvania Transformer Technology, Inc. (a Quanta Services company)Power & Substation (Oil-Filled)69 / 138 / 345 / to 765 kVNew: 65-110 weeks (5-50 MVA class); up to 4 years high-capacity · Used: 2-12 weeks
E-Saver OPAL series LV dry-typePowersmiths International Corp., Socomec GroupLV Dry-Typeappropriately K-ratedappropriately K-ratedNew: Quoted; 2024 factory expansion added capacity · Used: No used channel observed
GEAFOL / GEAFOL NeoSiemens Energy AG (Grid Technologies)Cast-Resin Dry-TypeNew: 20-32 weeks (dry-type class); large units longer · Used: Auction-cycle dependent
Sensformer connectivity platform (now within the Noedra portfolio)Siemens Energy AG (Grid Technologies)Digital & MonitoringNew: Ships embedded with host transformer · Used: Not traded separately

Which Transformer Do You Need

Indoor installation in a fire-rated space

Dry-type and cast coil units carry no liquid, so they avoid the containment, spill response, and fire-separation obligations that follow an oil-filled unit indoors. Cast coil buys sealed windings and better humidity tolerance at a higher price than ventilated dry-type. Dry-Type and Cast Coil Transformers: Selection, Sizing, and Where Each Belongs covers the detail.

Outdoor pad at the utility interface

Pad-mount units are the default at the service entrance: tamper-resistant enclosure, dead-front terminations, and no separate vault. Confirm DOE 2016 efficiency compliance and whether the fluid is mineral oil or a natural ester such as FR3. Pad Mount Transformers: Sizing, Configurations, and Current Lead Times covers the detail.

Space-constrained rooms with integrated switchgear

A unit substation ties primary switch, transformer, and secondary switchgear into one close-coupled lineup, removing cable runs and shortening the footprint. The cost is flexibility, and lead time is set by the slowest component in the lineup. Data Center Transformers: The Complete Selection and Procurement Guide covers the detail.

Nonlinear data center load

IT loads draw harmonic current, which heats a transformer beyond what its nameplate kVA implies. A K-rated or harmonic-mitigating unit is sized for that heating; a standard-rated unit has to be derated instead. Data Center Transformer Sizing Guide: Load Math, K-Factor, and Lead-Time Reality covers the detail.

Used and Surplus Transformers

New pad-mount and power transformer lead times run in years at the OEM, which is why schedule-driven projects look at surplus and used units. The lead-time column states what each dossier documents for new and used channels. SecondWatt holds no stock and sets no price: send the rating, voltage, and type and the request is routed to sellers holding matching equipment. List equipment you hold.

Pricing Tiers