An automatic transfer switch connects a load to one of two power sources, usually the utility and a generator. It moves the load to the generator when the utility fails and back when the utility returns, with no one at the switch.

Buying an automatic transfer switch for generator backup comes down to three decisions: how it transfers, whether its ratings hold at the fault current where it sits, and how much current its load draws. A critical facility adds a fourth, system-level question about restoration time, which the switch alone cannot answer.

Key Takeaways

  • An ATS runs on timers. ASCO's Group 5 controller defaults to a 1-second delay before signaling engine start, 30 minutes before retransfer after a failure, and 5 minutes of cooldown.
  • Closed transition cannot bridge a utility outage. It parallels two live sources only on planned transfers, for under 100 ms on ASCO switches; after a utility failure it transfers open.
  • The upstream device sets the fault rating. An ASCO J-frame 400 A switch at 480 V: 200 kA with fuses or specific breakers, 42 kA time-based in ASCO's July 2026 table.
  • Size from the load the switch carries. A 50 kVA, 208 V three-phase load draws about 139 A; dividing that kVA by power factor again gives about 173 A, calculated.
  • Switch timing is one part of a Type 10 system. In Cummins' 2019 outage sequence the generator takes up to 8.5 of the 10 seconds; the switch takes the rest.

What an automatic transfer switch does#

In its article "What is a transfer switch?", Schneider Electric lists six functions every automatic transfer switch performs: carry current continuously, detect a power failure, start the alternate source, transfer the load, sense the normal source's return and retransfer. Failure means voltage or frequency is out of range or absent. Transfer waits until the generator's voltage and frequency are acceptable.

Timers decide when each step happens. A short delay filters out momentary dips; another holds the load on the generator until restored utility power proves stable. Retransfer typically waits until the sources are within 5% on voltage and 2 Hz, and, where applicable, 5 degrees of phase angle, in Schneider Electric's description.

Transfer timers on two ASCO switch lines: default and adjustment range (ASCO 381333-126 R, 6/2026; ASCO Publication 3090 R11, 8/2016)#

Timer What it does ASCO 7000 Series, Group 5 controller: default (range) ASCO 300 Series suggested specification: range
Override momentary normal outage Delays the engine-start and transfer signals 1 s (0–6 s) 0–6 s
Transfer to emergency Waits after the generator is acceptable 0 (0–60 min 59 s) 0–60 min 59 s
Retransfer to normal after a failure Holds the load on the generator after the utility returns 30 min (0–60 min 59 s) 0–9 h 59 min 59 s
Retransfer after a test Same hold, after a test transfer 30 s (0–9 h 59 min 59 s) Not listed separately
Engine cooldown Runs the generator unloaded before shutdown 5 min (0–60 min 59 s) 0–60 min 59 s
Delayed-transition load disconnect Holds the switch in its center-off position 3 s (0–5 min 59 s), delayed-transition models 0–5 min 59 s

Defaults are from the Group 5 controller user's guide for the ASCO 7000 Series; ranges in the last column are from ASCO's 2016 suggested specification for the ASCO 300 Series. Factory defaults apply "unless otherwise specified on the order", so read the settings on any used switch. In Cummins' 2013 transfer switch brochure, PowerCommand controls for the Cummins OTPC name equivalent timers for engine start, transfer, retransfer and engine cooldown.

Diagram: the five steps of an automatic transfer, from sensing a utility failure to retransfer and generator cool-down, with the ASCO Group 5 default timer for each step.
Figure 1. The five timed steps of a transfer, with ASCO Group 5 controller defaults.

Transition modes: open, delayed and closed#

Transition mode is how the switch moves between sources, and each mode answers a different load question. According to Part 1 of ASCO's Transition Modes paper, open transition is break-before-make, about 30 to 50 milliseconds on ASCO switches depending on size. Delayed transition holds a center-off position, set from seconds to minutes, so motors and downstream transformers can shed stored energy.

Closed transition is make-before-break. Part 2 of ASCO's Transition Modes paper puts the overlap on ASCO switches at under 100 milliseconds, depending on capacity. It needs two live sources, so it works only on planned transfers such as tests and retransfer. After a utility failure only the generator is live, and Schneider Electric notes that the switch makes an open transfer with a momentary interruption. As ASCO's Part 2 paper notes, carrying a load through that gap takes stored energy, which is what a UPS supplies.

Soft-load transfer parallels the sources for a longer, user-selected time while the controller ramps generator output, avoiding a block load. It too falls back to an open transfer on an unplanned outage.

Transition modes compared: what each does and the question it raises (ASCO application papers, 2018; UL 1008 scope)#

Configuration What it does Question for the load
Open transition Breaks from one source, then makes to the other, in about 30–50 ms on ASCO switches Can the load ride through a short gap, or is ride-through provided elsewhere?
Delayed transition Holds a center-off position for seconds to minutes Do motors or transformers need time for stored energy to decay?
Closed transition Parallels two live sources on planned transfers, for under 100 ms on ASCO switches Are both sources in phase, and has the utility accepted momentary paralleling?
Soft load Parallels the sources and ramps generator load over a set time Is longer paralleling with the utility permitted at this site?
Bypass-isolation Adds a bypass path so the transfer switch can be isolated Can the switch be tested and serviced while the load stays on?
Diagram: four timelines showing when the normal source and the generator are connected during open, delayed, closed and soft-load transfer, with a short gap, a center-off hold, a brief overlap and a longer ramp.
Figure 2. When each source is connected during open, delayed, closed and soft-load transfer; not to scale.

Bypass-isolation is a maintenance arrangement rather than a transfer mode. UL 1008's ninth-edition scope, as UL Standards & Engagement publishes it, covers bypass/isolation switches, used to select a source by hand and "to provide for total isolation of an automatic transfer switch".

The ratings that decide suitability#

Continuous current and fault duty are separate checks. Schneider Electric says an ATS must carry "100 percent of its rated service current" continuously, and also any fault current that reaches it until breakers or fuses clear the fault.

The withstand and closing rating (WCR) states that fault duty, and the upstream protective device sets its value. One switch can carry three: with named current-limiting fuses, with the breakers it was tested with, and time-based, for any breaker clearing within a stated time. Revision 38 of ASCO Publication 1128 gives all three in a table dated 22 July 2026.

200 kA or 42 kA — an ASCO J-frame 400 A switch at 480 V is rated 200 kA with those fuses or breakers but 42 kA time-based at 0.05 seconds, and 35 kA time-based with an overlapping neutral.

The same switch was rated 50 kA with specific breakers in the May 2019 table of ASCO White Paper 110, so a maker's ratings change between editions. Ask for the rating label and the maker's table as of the quote date.

In ASCO Publication 1128, optional short-time ratings let a switch hold fault current while downstream breakers with trip delays clear first, for selective coordination. When UL added the short-time test in June 2002, its duration was the manufacturer's choice, from 0.1 to 0.5 seconds. A short-time rating runs ten times longer than a time-based one in Cummins' 2020 Transfer Switch Fundamentals training: 0.5 seconds (30 cycles) against 0.05 seconds (3 cycles).

Rating checks for one ATS: what each covers and what to request (ASCO Publication 1128; Cummins, 2020)#

Rating What it covers What to request
Continuous current The load current the switch carries at all times Ampere rating, voltage, frequency and poles on the nameplate
WCR, fuse-protected Fault current with named current-limiting fuses upstream kA at the system voltage, with fuse class and maximum size
WCR, specific breaker Fault current with named breaker models upstream kA, and the list of breakers the rating names
WCR, time-based Fault current with any breaker opening within a stated time kA and the time, for example 0.05 s
Short-time (optional) Holding fault current while downstream devices clear kA and duration, matched to the coordination study

A switch documented at 30 kA with a given breaker is unsuitable where 40 kA is available under that breaker, whatever its ampere frame.

According to UL Standards & Engagement, UL 1008, Transfer Switch Equipment, is in its ninth edition, published 13 July 2022 and last revised 25 August 2026. Its scope covers automatic, closed-transition, soft-load and bypass/isolation switches up to 1,000 V, and switches intended for use as service equipment. Ratings in ASCO's 2026 table were tested under the seventh edition, effective 1 November 2014, and the 2026 revision of UL 1008 relocated the closing test. Ask which edition a quoted rating was tested to.

Cummins' 2020 training describes a service-entrance-rated ATS as integrating the service disconnect in the switch assembly. Ask for its listing for use as service equipment; an ampere label says nothing about it.

Sizing an automatic transfer switch#

Automatic transfer switch sizing starts with a boundary drawn around the equipment the switch feeds. That may be a whole service, one generator-backed distribution board, a UPS input or a cooling branch. A generator may feed several switches, each with its own load and protection, so each switch is sized to its own load.

The load schedule behind each switch should state:

  • running demand and the basis for any demand or diversity factor;
  • continuous loads and how they are treated;
  • motor starting, restarting and transfer behavior;
  • UPS input demand, including losses and battery recharge;
  • loads added in later phases, and when an upgrade becomes necessary;
  • load-shedding controls and priorities.

For a balanced three-phase load, current in amperes is kVA × 1,000 ÷ (√3 × line-to-line voltage). From real power, it is kW × 1,000 ÷ (√3 × voltage × power factor). A kVA figure already contains the power factor, so dividing it by power factor again overstates the current.

Worked current examples for three balanced three-phase loads (illustrative; calculated)#

Load Calculation Line current (calculated)
50 kVA at 208 V 50,000 ÷ (√3 × 208) 138.8 A
40 kW load at 208 V, 0.8 power factor 40,000 ÷ (√3 × 208 × 0.8) 138.8 A
500 kW load at 480 V, 0.9 power factor 500,000 ÷ (√3 × 480 × 0.9) 668.2 A
Diagram: three worked examples of transfer-switch current from kVA or kW at 208 V and 480 V, each with its formula and result.
Figure 3. The sizing arithmetic for the three worked examples; arithmetic only, not a switch selection.

The first two rows are the same load: 40 kW at 0.8 power factor is 50 kVA. Dividing the 50 kVA by 0.8 again would give 173.5 A, about 25% too high (calculated). These rows are arithmetic only. They do not fix the frame, conductors, protective device or fault rating.

Use the equipment's own input data in place of an assumed power factor. Mixed single-phase loads need a phase-by-phase check, because a balanced formula can hide an overloaded phase.

Motors, UPS inputs, poles and the neutral#

Motor loads are where transition mode and sizing meet. A motor reconnected nearly in phase draws about its normal starting inrush, typically up to 6 to 8 times running current. Reconnected 180 degrees out of phase, it can draw 12 to 18 times, according to Part 1 of ASCO's Transition Modes paper.

ASCO White Paper 119 lists the remedies: in-phase transfer, motor-load disconnect circuits, delayed transition and closed transition. In-phase monitors transfer within a nominal 60 degrees. Generators are often sized with limited motor-starting capacity, so staggered transfer delays across several switches keep total inrush within it.

UPS-backed loads are sized from the UPS maker's input data, which differs from the IT output; the UPS sizing guide separates kW, kVA and redundancy.

Pole count is a grounding decision, settled before a used switch is sourced: Cummins ties the 3-pole or 4-pole choice to the system's grounding scheme. A separately derived generator has no direct connection to the normal source, neutrals included, and its neutral is bonded to ground. In Cummins' 2020 training, a non-separately derived system shares one neutral, bonded at the service.

Keeping a separately derived generator's neutral apart from the utility's takes a fourth, switched pole. Proper ground-fault sensing also allows only one neutral-to-ground connection on a neutral bus at a time.

Code basis: NFPA 110, NEC and UL 1008#

NFPA 110, the Standard for Emergency and Standby Power Systems, is in its 2025 edition, as NFPA's document page shows. Its scope covers power sources, transfer equipment and controls. The edition that applies is the one the jurisdiction has adopted.

The standard classifies a system three ways, in sections 4.2 to 4.4 of the 2016 edition as Cummins reprints them in a 2019 webinar. Class is the minimum time, in hours, at rated load "without being refueled or recharged". Type is the maximum time, in seconds, that the transfer switch's load terminals may be "without acceptable electrical power". Level ranks the consequence of failure: Level 1 applies where failure "could result in loss of human life or serious injuries".

In the 2022 edition, Table 4.1(b) gives Type 10 a restoration time of 10 seconds, according to an October 2022 NFPA 110 public input report. A Type 10 system is therefore a different classification from a Level 1 system.

The ten seconds belong to the whole system.

8.5 of 10 seconds — the generator's time to "Ready to Load" in Cummins' 2019 Type 10 sequence, after a start delay of up to 1 second and before a transfer of up to 0.5 seconds (10 seconds in all, calculated).

Fuel, coolant heaters and starting batteries can each affect whether the generator meets its share. An ATS operating time therefore cannot show system compliance alone.

The NEC, NFPA 70, is in its 2026 edition, as NFPA's document page shows. Adopted editions vary by US jurisdiction. Establish the adopted edition and whether each load is an emergency, legally required standby or optional standby system. For optional standby, UL 1008's ninth-edition scope excludes double-throw switches but covers automatic transfer switches built to its optional standby requirements, which it bars only in Canada.

Where ATS units sit in a data center#

In Cummins' 2020 layout of a paralleled system, the generator sets feed a distribution board, and that board feeds the transfer switches ahead of the loads. That generator bus is the subject of the guide to paralleling switchgear. Part 2 of ASCO's Transition Modes paper advises placing each switch close to the loads it serves.

Motor-heavy circuits behind transfer switches include air-conditioning compressors for data center cooling, as ASCO White Paper 119 notes. A switch can be enclosed, or an open type "intended for mounting in other equipment such as switchboards" under UL 1008's ninth-edition scope. The distribution equipment around it is covered in the low-voltage switchgear guide.

Static transfer switches are a different product: UL 1008's scope excludes "solid-state (static) transfer equipment", along with switches rated over 1,000 V. Downstream IT distribution choices are covered in ATS versus STS selection, and the redundancy tier around each switch in the data center redundancy guide.

What an ATS quotation should include#

A quotation is comparable only once its scope is complete. Ask for the continuous current, voltage, frequency, poles, transition mode, WCR basis, service-entrance status, bypass arrangement, enclosure, controls and communications. Price removal, freight, engineering, cable adaptation, installation, testing and commissioning as separate lines.

A used switch needs records that a new one ships with. The Group 5 controller keeps a log of its last 99 events and statistics that cannot be reset: total transfers, transfers caused by source failure and days energized. It also displays its software version and release date, according to ASCO's Group 5 user's guide.

Records for a used automatic transfer switch: what each shows and the gap to watch#

Record What it shows Gap to watch
UL 1008 label and nameplate Listing, model, serial number, ratings Missing label, or ratings that do not match the quotation
WCR documentation kA with the named fuse, breaker or time A headline kA with no protective-device conditions
Controller statistics and event log Transfers, failure transfers, days energized, last events Controller replaced with no record of the old counts
Controller software version Release loaded and its date A release the maker no longer supports
Test and maintenance records Transfer tests, inspections, repairs No record of tests under load
Drawings and photographs Outline, wiring and current condition Missing or modified components

Ask for the same records whichever family the switch belongs to; the ATS hub holds dossiers for the ASCO 4000 Series, GE Zenith ZTG, Kohler KCS and Russelectric RMTD.

FAQ: automatic transfer switches#

What is the difference between an automatic and a manual transfer switch?#

In Schneider Electric's description, a manual switch stays on one source until a qualified person recognizes the outage and operates it. A non-automatic switch also needs a person, but through local or remote controls. A temporary or rental generator connection is a separate arrangement, covered in the generator docking station guide.

How fast does an automatic transfer switch transfer?#

The contacts move in milliseconds; the timers and the generator take seconds. ASCO White Paper 119 notes that a switch needing about 40 milliseconds to operate lets 2.4 cycles pass at 60 Hz. For the transfer step, Cummins' 2020 list of common emergency-standby settings gives 0.5 to 1.5 seconds, by switch and application; its 2019 Type 10 sequence allows up to 0.5 seconds.

Can one ATS serve two generators?#

Yes, when the generators are paralleled first, so each ATS sees one combined alternate source. For paralleled systems, the smallest set on the paralleling bus should be able to carry all emergency loads, under the specification note in Cummins' 2019 Type 10 webinar.

Does a closed-transition ATS need the utility's agreement?#

According to Part 2 of ASCO's Transition Modes paper, utilities routinely permit closed-transition switching. But the local utility's requirements "must be understood" first, because the switch briefly parallels the generator with the grid. Cummins' 2020 training warns that utility safeguards and documentation "may add cost and complexity". ASCO's Group 5 controls raise an extended-parallel alarm if the sources stay paralleled past a factory-preset time.

Does the electrical code require a bypass-isolation switch?#

In some buildings. As published, section 700.6(C) of NFPA 70-2026, the US NEC, requires a means to bypass emergency transfer equipment without losing power and a means to isolate it. It applies where emergency loads are fed by a single feeder in the occupancies listed in 700.10(D)(1), according to NFPA's 2026 TIA 1903 proposal. NEMA proposed that interim amendment in 2026 to drop the occupancy limit and add exceptions, so check the adopted edition and any amendments.

Specifying the switch#

SecondWatt publishes equipment research and helps buyers source power equipment; it earns a fee when a sale it arranges closes. To source an automatic transfer switch, send the load schedule, one-line diagram, available fault current and transition mode through an equipment request. An owner with a surplus switch can see how SecondWatt works with sellers on the seller page.