Baker Hughes LM9000 Gas Turbines for Sale

Manufacturer: Baker Hughes

Baker Hughes LM9000 — gas turbine, 70.2 MWe
Baker Hughes LM9000

70-71 MWe aeroderivative gas turbine at up to 43.1% with direct drive at 50 or 60 Hz and a 36,000-hour supercore inspection interval.

This model is part of SecondWatt’s gas turbine research catalogue. Specifications and price observations are included where supported by sources. Equipment availability and commercial terms require confirmation.

Baker Hughes LM9000 aeroderivative gas turbine: 70.2-71.4 MWe at up to 43.1%, direct drive at 50/60 Hz, 36,000-hour supercore interval, DT70 mobile power.

The LM9000 is Baker Hughes' 70 MW-class aeroderivative gas turbine: 70.2 MWe at 42.8% for 50 Hz and 71.4 MWe at 43.1% for 60 Hz at the generator terminals, and 73.1 MW (98,029 hp) at 44.2% for mechanical drive, all at ISO conditions. Baker Hughes derives it from the GE90-115B aircraft engine and calls it "the most efficient gas turbine in the 65+ MW range".

The power turbine drives the generator directly at 3,000 or 3,600 rpm, so power-generation packages need no gearbox. A single annular combustor with dry low emissions is rated 15-25 ppm NOx without water. Inspections fall at 12,000 hours (borescope), 36,000 hours (supercore) and 72,000 hours (full engine). In mechanical drive the LM9000 can start a pressurized LNG compressor without a helper motor, per Baker Hughes.

In November 2025 Dynamis Power Solutions ordered LM9000s to build the DT70, a 70 MW mobile power unit, ten of them for 700 MW of oil and gas power, as part of a 25-turbine, 1.3 GW aeroderivative order. The LM9000 sits between the LM6000 (about 50-57 MW) and the intercooled LMS100 (about 108-113 MW) in output; it is gas-only today, with dual fuel in development per Baker Hughes' 2025 overview.

Why it matters

At 43.1% (60 Hz) at the generator terminals and with direct drive, the LM9000 matches the intercooled LMS100PB+ (43% per Baker Hughes) in simple-cycle efficiency at about two-thirds of the output, without water for NOx control and with a 36,000-hour supercore interval. Assessment: its constraints for power projects are gas-only fuel today, up to 5% hydrogen, and a young fleet with little published operating history.

Who buys it

LNG developers using it as a refrigeration-compressor driver, mobile and distributed power providers (Dynamis Power Solutions' DT70), and simple-cycle, cogeneration and combined-cycle power developers that want about 70 MW per unit at aeroderivative efficiency. Baker Hughes lists onshore and offshore LNG, pipelines, industrial use and combined-cycle plants as applications.

Role in the data center

Assessment: a 70 MW behind-the-meter block, two to four units per 150-300 MW phase plus a spare, at about 43% simple-cycle efficiency without water, or the gas turbine in a combined-cycle block (Baker Hughes claims 56% in cogeneration). Mobile DT70 units bring the same engine on a relocatable package. Baker Hughes publishes no start-to-load time for the LM9000, so confirm start and black-start capability per package.

Key specifications

Power-generation output, ISO, generator terminals, 50 Hz70.2 MWe
Power-generation output, ISO, generator terminals, 60 Hz71.4 MWe
Power-generation efficiency, 50 Hz / 60 Hz42.8 / 43.1 %
Power-generation heat rate, LHV, 60 Hz (calculated from 43.1%)7917 Btu/kWh
Mechanical-drive shaft output, ISO73.1 (98,029) MW (hp)
Mechanical-drive efficiency, ISO44.2 %
NOx, dry low emissions15-25 ppm
Exhaust temperature, power generation / mechanical drive456 / 455 C
Power-generation speed, direct drive3,000 / 3,600 rpm
Mechanical-drive speed range (2025 overview)2,400-3,780 rpm
Mechanical-drive rated speed (product page)3429 rpm
Borescope inspection interval12000 hours
Supercore inspection interval36000 hours
Full-engine inspection interval72000 hours
Package, L x W x H13.3 x 5 x 18.2 m
Package weight (2025 overview)77 tons
Fuel flexibility, modified Wobbe index36-55 MWI
Hydrogen capabilityup to 5 % by volume
Cogeneration efficiency (Baker Hughes claim)56 %
Dynamis DT70 mobile unit output (one LM9000)70 MW

Technical summary

Baker Hughes rates the LM9000 at 70.2 MWe and 42.8% (50 Hz) and 71.4 MWe and 43.1% (60 Hz) at the generator terminals, and 73.1 MW (98,029 hp) at 44.2% for mechanical drive, at ISO conditions (natural gas, 15 C, sea level, 60% relative humidity, no inlet or exhaust losses). NOx is 15-25 ppm and exhaust temperature 456 C (455 C in mechanical drive). Power generation runs at 3,000 or 3,600 rpm direct drive. Inspections fall at 12,000, 36,000 and 72,000 hours. The package measures 13.3 x 5 x 18.2 m and the 2025 overview lists 77 tons. Fuel is gas only, 36-55 modified Wobbe index, with up to 5% hydrogen. Heat rate calculated from 43.1% is about 7,917 Btu/kWh LHV.

Major variations

Baker Hughes sells the LM9000 in power-generation packages for 50 Hz (70.2 MWe) and 60 Hz (71.4 MWe), both direct drive, and in a mechanical-drive package (73.1 MW shaft) for compressors such as LNG refrigeration trains. Dual fuel (gas plus liquid) is in development per the 2025 overview. Dynamis Power Solutions' DT70 packages one LM9000 as a 70 MW mobile unit. The LM9000 is a different engine from the LM6000 and the intercooled LMS100.

Configurations and options

Baker Hughes supplies a modular package for faster installation, measuring 13.3 x 5 x 18.2 m. Options that change price or lead time are the frequency (50 or 60 Hz generator), the NOx level within 15-25 ppm, simple-cycle, cogeneration or combined-cycle scope, mobile packaging by a packager, and the service agreement covering supercore and full-engine exchanges.

Compatibility and dependencies

Fuel is natural gas only, within a 36-55 modified Wobbe index and up to 5% hydrogen; sites needing liquid backup fuel have no LM9000 option until the dual-fuel system is released. Direct drive at 3,000 or 3,600 rpm fixes the generator frequency to the package. Confirm the fuel-gas supply pressure requirement and any compression against the package datasheet.

Planning price band

Modelled planning estimate: $1.05M–$2.20M/MW · $1,050–$2,200/kW · $74.97M–$157.08M per unit (LM9000, 60 Hz, 71.4 MW; New OEM; very low confidence; gt-planning-v3, as of 2026-11-03). Not a quote or an observed sale price. New OEM gas turbine generator package, equipment scope. Inclusions and delivery terms vary by offer and are subject to confirmation. Not a project budget: EPC, BOP, installation and financing sit outside this band.

Newest large aero; no used fleet.

What drives the price

Power-generation frequency or mechanical-drive package; simple-cycle, cogeneration or combined-cycle scope; mobile packaging; the NOx level; service agreement terms including spare supercore access; the delivery slot; and, for used units, hours, starts and supercore inspection status.

Lifecycle and maintenance

Baker Hughes rates borescope inspection at 12,000 hours, supercore inspection at 36,000 hours and full-engine inspection at 72,000 hours. The supercore can be exchanged rather than overhauled in place, which shortens outages where a spare core is available. Baker Hughes does not publish an MTBF figure or an LM9000 fleet count as of October 2026.

Thermal and emissions profile

The single annular dry-low-emissions combustor is rated 15-25 ppm NOx without water injection, which Baker Hughes notes eliminates water use for emissions abatement. Fuel is gas only with up to 5% hydrogen by volume per the 2025 overview.

Common failure points

LM9000 ratings at 50 and 60 Hz

Fuel and emissions

Maintenance and availability

Compare offers on

Seller checklist

What sets the value

Value rests on records: engine and power-turbine serial numbers, operating hours and starts, borescope and supercore inspection reports, DLE tuning and emissions tests, generator test records, controls software licences and the service agreement status.

How much power does an LM9000 produce?

Baker Hughes rates it at 70.2 MWe and 42.8% at 50 Hz and 71.4 MWe and 43.1% at 60 Hz at the generator terminals, and 73.1 MW at the shaft for mechanical drive, all at ISO conditions with no inlet or exhaust losses.

Can an LM9000 run on liquid fuel or hydrogen?

Baker Hughes' 2025 overview describes the LM9000 as gas-only with dual fuel in development and up to 5% hydrogen by volume.

What is the Dynamis DT70?

A 70 MW mobile power unit that Dynamis Power Solutions builds on one LM9000. In November 2025 Dynamis ordered ten LM9000s for 700 MW of DT70 units as part of a 25-turbine, 1.3 GW order from Baker Hughes.

What are the LM9000 maintenance intervals?

Baker Hughes rates borescope inspection at 12,000 hours, supercore inspection at 36,000 hours and full-engine inspection at 72,000 hours.

Inspection checklist

Confirm the engine and power-turbine serial numbers and the package type from the nameplates. Obtain operating hours, starts and trip history. Review borescope reports against the 12,000-hour interval and the status of the 36,000-hour supercore inspection. Confirm the NOx rating and DLE tuning records. Check generator test results and vibration trends, controls software licences and the service agreement, including access to a spare supercore. Agree acceptance criteria before payment.

Procurement channels

Assessment: used LM9000 units are rare because the fleet is young.

Regional notes

Separate 50 Hz (70.2 MWe) and 60 Hz (71.4 MWe) ratings apply, both direct drive. In the United States a new LM9000 falls in the medium band of NSPS Subpart KKKKa (about 565 MMBtu/h LHV and 626 MMBtu/h HHV at ISO, calculated). Baker Hughes lists onshore and offshore LNG, export terminals and pipelines among its applications.

Content owner: Gary Martin, SecondWatt