GE 7F.05 and 7HA Gas Turbines: Specifications and Pricing
Manufacturer: GE Vernova

GE Vernova 7F.05 and 7HA, 60 Hz heavy-duty gas turbines
This model is part of SecondWatt’s gas turbine research catalogue. Specifications and price observations are included where supported by sources. Equipment availability and commercial terms require confirmation.
Compare GE 7F.05 and 7HA gas turbines, 60 Hz reference ratings and pricing scope. Distinguish turbine equipment from whole-plant values.
GE 7F.05 and 7HA gas turbines are separate equipment families for 60 Hz projects. Compare the exact model and installed configuration before evaluating output, service history or price. A 7F quotation should not be treated as interchangeable with a 7HA proposal.
GE 7F.05 and 7HA reference ratings
| Model | Family | OEM simple-cycle net output | Frequency |
|---|---|---|---|
| 7F.04 | F-class | 201 MW | 60 Hz |
| 7F.05 | F-class | 239 MW | 60 Hz |
| 7HA.02 | H-class | 384 MW | 60 Hz |
| 7HA.03 | H-class | 430 MW | 60 Hz |
Sources: GE Vernova 7F and 7HA, reviewed September 25, 2026. These reference ratings do not establish an offered unit's site performance. GE's current 7HA main table lists.02 and.03; any 7HA.01 specification belongs in a separate historical configuration record with its own source.
GE 7F and 7HA gas turbine pricing
The pricing research reviewed here does not establish a comparable equipment asking-price band for these families. Whole-plant transaction values can include assets and rights beyond turbine equipment and should remain separate from turbine purchase comparisons.
Request an itemized scope identifying the gas turbine, generator, controls, auxiliaries and any steam-cycle equipment. State whether the transaction covers loose equipment, an installed plant or another commercial arrangement. Confirm condition, modifications, dismantling responsibility and contractual delivery milestones.
Configuration and remaining-life review
For a 7F offer, document the installed hardware and completed upgrades rather than assigning a current catalogue rating. For a 7HA offer, identify the exact variant and service documentation. In either case, request component identity, operating history, inspection reports and applicable OEM guidance. A qualified reviewer should establish acceptance criteria and maintenance requirements for the actual unit.
Request equipment. For a 50 Hz project, compare the GE 9HA.
Key specifications
| Simple-cycle net output, 7F.04 (60 Hz) | 201 MW |
|---|---|
| Simple-cycle net output, 7F.05 (60 Hz) | 239 MW |
| Simple-cycle net output, 7HA.02 (60 Hz) | 384 MW |
| Simple-cycle net output, 7HA.03 (60 Hz) | 430 MW |
Published cost benchmarks
Cost figures from filings and published studies. They describe budgets or project costs, not equipment prices.
- $108.8M · 7F.05 1x0 North Jax
- $123.1M · 7HA.01 1x0 North Jax
- $169.2M · 7HA.02 1x0 North Jax
- $3300M · 7HA.03
- $525M · 7F.05
- $625M · 7F.05
- $2300M · 7HA.03
- $2700M · 7HA.03
- $548.7M · 7HA.03 · 2028 dollars
- $1909.6M · 7HA.03 two-train combined cycle, PJM CONE CC reference · 2028 dollars
- $1800M · 7HA.03
- $2300M · 7HA.03
- $159M · 7HA.03 · 2028 dollars
- $53M · 7HA.03 · 2028 dollars
- $421M · 7HA.03 · 2028 dollars
- $526M · 7HA.03 · 2028 dollars
- $1819.2M · 7HA.03 2 x · 2028 dollars
- $647.8M · 7HA.03 simple-cycle reference · 2028 dollars
- $449.9M · 7HA.03 1x0 simple cycle, SCR, dual fuel · 2024 dollars
- $656M · 7HA.03 1x0 simple cycle, SCR, dual fuel · 2024 dollars
- $551M · 7HA.03 1x0 simple cycle, SCR, dual fuel · 2024 dollars
- $831M · 7HA.03 1x0 simple cycle, SCR, dual fuel · 2024 dollars
- $373.8M · 7HA.02 1x0 simple cycle, no SCR, dual fuel · 2024 dollars
- $568M · 7HA.02 1x0 simple cycle, no SCR, dual fuel · 2024 dollars
Supply, delivery and overhaul
3 units listed without public prices.
- Manufacturer-wide delivery estimate: 36 months
Content owner: Gary Martin, SecondWatt