Northern Virginia Data Center Market and Power
Review Northern Virginia’s published market measures alongside the questions that determine a site’s power requirement. The figures below use CBRE’s Northern Virginia wholesale market reporting; they are not a census of every data center in the region. Keep that research separate from the utility service plan and equipment requirements for your own project.
Published market snapshot: H1 2026
| Observation | CBRE reported value | Reporting basis |
|---|---|---|
| Market inventory | 4,496.5 MW | H1 2026 snapshot |
| Capacity under construction | 2,420.2 MW | H1 2026 snapshot |
| Colocation vacancy | 0.24% | H1 2026 snapshot |
| Net absorption | 467.6 MW | Activity during H1 2026 |
H1 2026 covers January through June. The snapshot reporting period ends 2026-06-30; net absorption describes activity during the half-year. These are dated publisher observations, not measurements taken when you open this page.
The vacancy value links to CBRE’s Northern Virginia chapter. Inventory, construction and net absorption link to the overview. Keep those measures separate when preparing a project brief; do not add them into a combined capacity total or use them to size a generation package.
Establish the site-specific service plan
For a site seeking Dominion Energy service, start with its service-territory check. Dominion asks prospective customers to confirm that their site is within its territory before submitting a request.
Dominion lists a site plan, load letter and load ramp schedule among the typical customer inputs. Its guidance describes service delivered in stages and a power plan developed for the particular site, with timing dependent on the customer’s needs and location.
Use that process to document the assumptions for an actual address. Ask the project team which milestones are confirmed, which remain contingent, and who will update the plan as the load changes. Confirm the serving utility before applying Dominion’s process to a site.
Procurement questions for a phased load
SecondWatt procurement guidance. Keep the first occupied phase, later load increases and ultimate campus design separate in the requirements file. For each phase, ask:
- What load and operating duty must the equipment support?
- Which electrical interfaces, voltage and frequency must the engineering team confirm?
- Is the package being evaluated for outage backup, temporary operation or another defined duty?
- What components, controls and supporting documents are included or excluded?
- Which inspection, testing, delivery and acceptance requirements must the offer address?
Have the project’s electrical team confirm the arrangement before matching a model. Record changes to the service plan alongside the equipment requirement so a sourcing partner can evaluate the same scope.
Equipment owners and sourcing partners should prepare model and configuration records, condition and maintenance evidence, package inclusions, and the proposed release or removal arrangements. Share identifying equipment documents and commercial terms through the private inquiry process.
Check facility evidence and boundaries
Before using a facility record in procurement work, verify the source for its capacity, floor area, operating status and commissioning date. Check whether a rating describes a campus, building, IT load or another power basis.
Reconcile campus summaries and individual buildings before counting them together. Check the actual address and the publisher’s geographic coverage before assigning a facility to a Northern Virginia comparison.
Turn the research into an equipment inquiry
Use the equipment model dossiers to investigate a model, configuration and documentation requirements. Prepare the buying requirement or equipment offer before requesting an introduction. SecondWatt holds no inventory; a model dossier or data-center reference does not establish that a particular unit is available.